Roof Trusses going up

Today (17/11/2020) the block work has been finished apart from the gables that will be completed once the trusses are up.

The trusses are lifted and secured into place, this will take the whole of today and then we will continue by building the gables, insulating the roof and laying ply down ready for the steel roof to be fitted at the start of the new year. Before the steel is fitted the roof will be made water tight and the windows and doors will be installed next week and the tiling of the floors will commence. Videos and updates to come.